Broadband News

News, views and analysis

Two more RFS delays

15 Feb 2005 | 22.13 Europe/London
Two more exchanges have had their RFS dates pushed back. Fortunately the delays are relatively short this time. Once again blocked ducting has been the cause of the delays, and the ammended dates are shown below.

















Exchange Old RFS date New RFS date
Blakesley 23/02/2005 31/03/2005
Wigmore 16/02/2005 31/03/2005

With only 821 exchanges remaining on the RFS list, we should hopefully see fewer delays as the deployment teams are spread less thinly on the ground.

On a side note, the server upgrade was completed at the weekend. Part of the upgrade was to move to a new version of PHP and Apache which have caused a few issues with some of the older code in the site. These errors should now have been resolved, but please drop me an email if you spot any problems.